This construction method uses both manpower and machines for excavation while also constructing retaining walls using steel corrugated sheets and ring frames. The ground is excavated until a determined depth and then reinforcing rods are assembled inside the underground shaft. The retaining material is then removed while concrete is poured in to construct the shaft.

Chicago (Board) Construction

Features

  • Can be used in narrow sites and on sloping ground, as well as from excavated surfaces
  • Enables large-caliber excavation and expansion of the base area.
  • Enables excavation of even extremely hard ground such as rock supporting layers.
  • Can directly observe and confirm the supporting soil